Bid opening held March 14, 2006.
Panzica Construction Co, the Board's Construction Manager for the Project, reviewed and evaluated the bids received, considered the responsibility of each of the apparent low bidders, considered the alternates included on the bid form for work and recommended to the Board the following bidders as the lowest responsible bidders for the specified base bid and selected alternates for the bid package:
General Trades Contract Infinity $9,579,550
Plumbing Contract Commerce $314,070
HVAC Contract T.H. Martin $880,715
Electrical Contract Doan Pyramid $2,178,491
TOTAL $12,952,826
The Board met this morning and passed a resolution to award bids outlined
above.
Letters of intent from the Construction Manager were just issued.
Contracts and more detailed scope of work document will be issued within the
next
fourteen days.
Actual work on the project site will begin on April 3, 2006.
Revised Target Dates: December 2005 - March 2006
Construction Manager Preliminary Budget Check - December 1 - December 16, 2005
Board Review and Approval to Proceed - December 19 - December 23, 2005
Design Team’s CBLH finalizes redesign deliverables/CM incorporate redesign into front ends - December 26 - January 18, 2005
Board Approval to go out for bid - January 19 - January 25
Construction Manager reviews documents for addendum issue if necessary - January 25, 2006
Bid Document reproduction - January 26 - 27, 2006
Bid Advertisement and Bid Phase - February 9 - March 2 (actually February 22 float if addendums are issued)
Pre-bid Meeting - February 16, 2006, 2 p.m., Main Library Auditorium
Bid Opening - March 9, 2006, Noon, Main Library Auditorium
CM Post Bid Review & Recommendation to award/Board Approval/Primes Contracts issued - March 9, 2006
Tentative Construction Start - March 20, 2006